SR 180 West
SR 180 West ID: A
Project Description
Create passing lanes in each direction on State Route 180 West (Whitesbridge Road) from Yuba Ave to James Ave.
Funding
Measure C Extension
$12.28 Million
Progress
Project A COMPLETED 2018
Design – Completed
Right of Way (ROW) – Begin: 2012 End: 2013
Construction – Begin: 2013 End: 2018
SR 180 East Seg III
SR 180 East Seg III ID: B
Project Description
Widen State Route 180 East from Temperance to Academy Ave to a 4-Lane Divided Expressway.
Funding
Federal Aid
$19.61 Million
STIP
$28.27 Million
Original Measure C
$30.56 Million
Total Cost
$78.443M
Progress
PROJECT COMPLETED.
Original Measure C Program Funds.
This project was accelerated using Original Measure C funds and leveraging Federal Stimulus ARRP funds.
Began: 2009 Completed: 2011
SR 180 East Seg IV
SR 180 East Seg IV ID: C
Project Description
Widen State Route 180 East from Academy to Trimmer Springs to a 2-Lane Expressway on 4-Lane right-of-way. This project has been accelerated using Original Measure, State and Local Partnership and Extension Measure Regional Transportation Mitigation Fee
Funding
Measure C Extension
$9.44 Million
RTMF
$3.47 Million
Original Measure C
$13.13 Million
SLPP
$11.55 Million
Progress
Project C COMPLETED 2013
Part of the Original Measure C Program.
Design – Completed;
ROW – Completed
Construction phase accelerated to began in 2013.Amount Expended in FY 17/18: $6,300
SR 180 East Seg V
SR 180 East Seg V ID: D
Project Description
Widen SR180 East to a 2-Lane Expressway from Trimmer Springs to Frankwood Avenue. The Design and part of the Right of Way portion of this project was accelerated using $13.589 Original Measure funds.
Funding
STIP
$57.76 Million
Original Measure C
$13.59 Million
Measure C Extension
$19.6 Million
Total Cost
$90.948M
Progress
Part of the Original Measure C Program.
Design – In Progress
ROW – In Progress
Construction Phase – Begin: 2016 End: 2020Amount Expended in FY 17/18: $6,300
Friant Road Widening
Friant Road Widening ID: E
Project Description
Widen Friant Road from Copper Ave to Millerton to a 4-Lane.
Funding
Measure C Extension
$4.12 Million
Total Cost
$4.120 Million
Progress
PROJECT COMPLETED
Began: 2008
Ended: 2009
Golden State Boulevard
Golden State Boulevard ID: F
Project Description
Corridor and Economic improvements to Golden State Boulevard from American Ave. to Tulare County line. Costs for Right-of-Way and Construction to be determined after the design portion is completed.
Funding
Measure C Extension
$6.83 Million
Progress
Design – In Progress
Environmental – Begin: 2013 End: 2014
ROW and Construction to be programmed in the Long-Term Program which was under review at COG beginning 2016.
Total Project Cost to be determined after Design. 2021 scheduled completion.
SR 269 Bridge Improvement
SR 269 Bridge Improvement ID: G
Project Description
Construct a new bridge and channel on SR269 between SR198 and Huron to address seasonal road closures due to flooding. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$39.8 Million
Progress
This project’s funding and schedule will be programmed in the Long-Term Program which began the review process at COG in 2014.
Scheduled for 2021 completion.
SR 180 West I5 Extension
SR 180 West I5 Extension ID: H
Project Description
Route Adoption Study to extend State Route 180 West to Interstate 5 as a 3-Lane undivided highway. This $82.761 million project will be scheduled in the Long-Term Regional Transportation Program which will begin review in 2014.
Funding
Funding Source TBD
$82.76 Million
Progress
The funding and schedule for this project will be programmed in the Long-Term Program which began the review process by COG in 2014.
No funding available.
Mountain View Ave Widening
Mountain View Ave Widening ID: I
Project Description
Widen Mountain View Ave to a 4-Lane Divided road from Bethel Ave to the Tulare County line.
Funding
Measure C Extension
$15.22 Million
SLPP
$8.84 Million
Progress
Project I COMPLETED 2018
Design – Complete
ROW – Complete
Construction – Begin: 2012 End: 2018
Academy Ave Widening
Academy Ave Widening ID: J
Project Description
Widen Academy Ave from Manning Ave to Industrial Way in Parlier. PROJECT COMPLETED 08/12 WITH $1.6 IN COSTS SAVINGS.
Funding
Measure C Extension
$1.95 Million
Progress
Project J COMPLETED 2012
Design/Right of Way – COMPLETED
Construction – COMPLETED
SR99 American Ave Interchange Improvement
SR99 American Ave Interchange Improvement ID: K
Project Description
Improve American Avenue Interchange on State Route 99. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$10.38 Million
Progress
The funding and schedule of this project will be programmed in the Long-Term Program which began the review process at COG in 2014. Scheduled for 2024 completion.
I-5 Interchange Improvement
I-5 Interchange Improvement ID: L
Project Description
Construct Interchange Improvement at the State Route 99 Interstate 5 Connection. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).
Funding
Funding Source TBD
$18.24 Million
Progress
The funding and schedule for this project will be set in the Long-Term Program which began the review process at COG in 2014. Scheduled for 2027 completion.