Project Highlights
Here are some of Measure C’s biggest projects in the City of Sanger so far!
Reconstruction Projects
Project Description
Measure C paid for street repairs that made improvements throughout the city.
Project Location
- Hume Dr / Forest Lane / Eastwood Ave – Hume Dr from Bennett Way to Eastwood Ave; Forest Ln from Tucker Ave to Hume Dr; Eastwood Ave from Tucker Ave to Hume Dr
- Rawson Ave – 14th St to Hoag Ave
- DeWitt Ave – Hoag Ave to 14th St
- I Street – 5th St to 10th St
- J Street – Annadale Ave to Edgar Ave
- K Street – Annadale Ave to Edgar Ave
- Almond Ave – K St to Faller Ave
- 8th Street – L St to Faller Ave
- Hill Ave / Church Ave / West Ave – Hill Ave from Church Ave to Canal Dr; Church Ave from West Ave to O St; West Ave from Church Ave to Canal Dr;
Project Photos


2021 Pavement Condition Survey Update
Project Description
This survey helped the city plan and focus on future road work.
Project Location
- Citywide
Pedestrian Improvements
Project Description
These projects enhanced walkability throughout the city.
Project Location
- Canal Drive – Greenwood Ave to Hill Ave
- Annadale and Lily Ave Pedestrian Crossing – Annadale Ave & Lily Ave Intersection
Bethel Avenue Bicycle Lanes and Pedestrian Improvements
California Avenue Alignment Study
Project Description
This study looked at ways to improve traffic flow and connections in the area.
Project Location
- Indianola Ave to Academy Ave
More Impact in Sanger
What else has Measure C done for Sanger?
Measure C also roadways on Vine, 3rd, O, Park, Cherry, 7th, and West Avenue from 7th to 3rd. Measure C made intersections safer, such as the one at Church and Harrison. It improved sidewalks, traffic signals, and access for people with disabilities. Plus, it repaved roads, added bike lanes, and built the Sanger Pedestrian Trails.
Measure C funding helped to create long-term plans to boost city infrastructure, to get state and federal grants by providing matching funds and to pay for professional planning and construction services.
Funding Received
2007-2024 Funding Totals to Date
Program(s)
Measure C Funds*
Street Maintenance
$4,856,279.26
ADA Compliance
$161,513.68
Flexible Funding
$4,695,138.23
Total
$9,712,931.17*
Pedestrian/Trails – Rural
$996,928.90
Bicycle Facilities
$254,524.55
Total
$1,251,453.45 *
*This total includes interest earned while saving up for big projects. That means that the amount spent on your community is more than the amount collected from sales tax.